DEVELOPMENT PROGRESS LRT JABODEBEK

  • 1st December 2021 GMT+7
The vehicle crosses next to the LRT (Light Rail Transit) development project in Jakarta, Wednesday (1/12/2021). The development progress of the project LRT Jabodebek stage I overall has reached 88.18 percent with the cross-service details of I Cawang-Cibubur at 93.96 percent, service traffic II Cawang-Dukuh Top 88.31 percent, service traffic III East Cawang-Bekasi 92.57 percent, Depo building 59.89 percent and targeted will operate in August 2022. ANTARA PHOTO/Packaging Reviyanto/foc.
Related photo
Standard
Image information
Image size
4000x2667
File size
2.04 MB
Created
01/12/2021 14:05 WIB
Photographer
Dhemas Reviyanto
Editor
Fanny Octavianus