PROGRESS CONSTRUCTION TOLL VESSELS SEXY II AND III

  • 16th December 2021 GMT+7
Toll Trans Sumatra’s Great-Palembang-Betung (Kapal Betung) Sexy II JalintimÃMusi Landas in Pulo Kerto Village, Gandus, Palembang, South Sumatra, Thursday (16/12/2021). The Toll Ship Work progress is Sexy II JalintimÃMusi Landas throughout 24,9 km has reached 33,68 percent, sexy III Musi Landas-Betung throughout 44,29 km has reached 6.71 percent while for the overall land logging has reached 85.86 percent or 1.694 fields. ANTARA PHOTO/Nova Wahyudi/rwa.
Related photo
Standard
Image information
Image size
2029x3000
File size
1.85 MB
Created
16/12/2021 16:20 WIB
Photographer
Nova Wahyudi
Editor
Puspa Perwitasari