PROGRESS CONSTRUCTION TOLL VESSELS SEXY II AND III
Workers complete the development of the Toll Road Project Trans Sumatra ruas Kayu Agung-Palembang-Betung (Kapal Betung) sexy II Jalintim– Landas Village in Ibul Besar III Village, Pelulutan, Ogan Ilir (OI), South Sumatra, Thursday (16/12/2021). The progress of workmanship toll vessels Sexy II Jalintim–The Landas solution throughout 24,9km has reached 33,68 percent, sexy III Musi Landas-Betung throughout 44,29 km has reached 6.71 percent while for the overall land logging has reached 85.86 percent or 1.694 fields. ANTARA PHOTO/Nova Wahyudi/rwa.