MRT Jakarta development progress
A number of workers complete the MRT Jakarta phase 2A CP201 development project in Glodok, Jakarta, Tuesday (9/5/2023). According to the data of PT MRT Jakarta (Perseroda) per 25 April 2023, the 2A MRT Jakarta phase development progress for CP 202 (Large Harmoni-Sawah Relocation) has reached 12.34 percent while for CP 203 (Stasiun Glodok and City) has reached 32.43 percent with the coverage of work include protection and relocation of utility, the work of channel decking, the old JPO disassembling, the long halte disassembling of Harmoni, and the transjakarta pile pit ANTARA PHOTO/Gover Pradipta/YU
Related photo