MINISTER ICEDM VISIT PLTP LAHENDONG
The Minister of ESDM Ignasius Jonan (right) was paired with the Governor of North Sulawesi Olly Dondokambey (left) and the Director of Operation of Pertamina Geothermal Energy Ali Mundakir (mid) when reviewing the progress of PLTP Lahendong units 5 and 6 in Tomohon, North Sulawesi, Saturday (26/11). Pertamina Geothermal Energy is successful to accelerate the forced acceleration of PLTP Lahendong units 5 and 6 with investment value of 228,7 US Dollar, where the 5 units succeeded in September 15th, 2016 or 107 days faster than the initial deforestation of December 26, 2016 and the 6 units expected to finish December 2016, advanced from the initial plan of June 2017. ANTARA PHOTO/Akbar Nugroho Gumay/pd/16