REMOTE AREA POWER SERVICE
General Manager PLN Region NTB Rudi Purnomoloka (left) witness citizens turn PLN electricity for the first time in Gili Gede Indah Village, Sekotong District, West Lombok, NTB, Thursday (14/6). To channel electricity from Lombok Island to Gili Gede through the Village Electricity Program (Lissa) PLN builds two marine wires of 20 kilo Volt (kV) each along 2.4 kilometer circuit (kms) as well as Medium Voltage Network (JTM) 3.64 kms, Low Voltage Network 6,64 kms, and four substations with a total capacity of 520 kilo Volt Ampere (kVA) with total investment value reaches Rp 19 billion. ANTARA PHOTO/Ahmad Subaidi/aww/18.