MANDALIKA CIRCUIT SUPPORT FACILITIES
The "Medical Center" Mandalika International Street Circuit facility in Special Economic Area (KEK) Mandalika, Pujut, Praya, Central Lombok, NTB, Monday (13/9/2021). Currently the construction of Mandalika circuit supporting facilities such as "Medical Center" and "Helipad" has reached a 100 percent progressive or has been completed, while the development of "Race Control Building" reaches the progress of 92.25 percent and "Pit Building" has 100 percent complete the foundation and the two buildings is targeted to be completed in October 2021. ANTARA PHOTO/Ahmad Subaidi/foc.