MANDALIKA CIRCUIT SUPPORT FACILITIES

  • 13th September 2021 WIB
MANDALIKA CIRCUIT SUPPORT FACILITIES
A worker crosses near the building facilities "Race Control" Mandalika International Street Circuit in the Special Economic Area (KEK) Mandalika, Pujut, Praya, Central Lombok, NTB, Monday (13/9/2021). Currently the construction of Mandalika circuit supporting facilities such as "Medical Center" and "Helipad" has reached a 100 percent progressive or has been completed, while the development of "Race Control Building" reaches the progress of 92.25 percent and "Pit Building" has 100 percent complete the foundation and the two buildings is targeted to be completed in October 2021. ANTARA PHOTO/Ahmad Subaidi/foc.