Workers set rail bearings (slab track) using gantry crane heavy equipment in Slab Track PT WIKA Beton Factory, Karawang, West Java, Wednesday (18/5/2022). PT WIKA Beton has been producing track slabs for Jakarta-Bandung Rapid Train projects (KCJB) as much as 14.786 units from 30.177 required track slab units that have been completed two weeks faster than previously scheduled namely at the end of May 2022, while the rest was produced by Sinohydro as much as 15.391 units. ANTARA PHOTO/Asprilla Dwi Adha/wsj.