CONCRETE WIKA COMPLETED PRODUCTION OF KCJB RAIL BEARING

  • 18th May 2022 WIB
CONCRETE WIKA COMPLETED PRODUCTION OF KCJB RAIL BEARING
Workers set rail bearings (slab track) using gantry crane heavy equipment in Slab Track PT WIKA Beton Factory, Karawang, West Java, Wednesday (18/5/2022). PT WIKA Beton has been producing track slabs for Jakarta-Bandung Rapid Train projects (KCJB) as much as 14.786 units from 30.177 required track slab units that have been completed two weeks faster than previously scheduled namely at the end of May 2022, while the rest was produced by Sinohydro as much as 15.391 units. ANTARA PHOTO/Asprilla Dwi Adha/wsj.

The caption is automatically translated by application. Click here for the Bahasa Indonesia version.

Related photo
Tags:
Image information
Image size
4000x2667
File size
2.11 MB
Created
18/05/2022 15:10 WIB
Photographer
Asprilla Dwi Adha
Editor
Widodo S Jusuf