PROGRES MRT FASE 2A CP201 MONAS

  • 21 Maret 2023 13:15 WIB
PROGRES MRT FASE 2A CP201 MONAS
Workers run in the tunnel of the MRT Jakarta-phase 2A CP201 line development project in the National Monument area (Monas), Jakarta, Tuesday (21/3/2023). According to the data of PT MRT Jakarta (Perseroda), the construction of CP 201 (Stasiun Thamrin and Monas) phase 2A MRT Jakarta has reached 53,03 percent which with the progress including emergency ladder casting access substation, cutting 'kingpost' station, casting station column, installation of OTE Duct, and the workmanship of wall ventilation tower. ANTARA PHOTO/M Risyal Hidayat/aww.

The caption is automatically translated by application. Click here for the Bahasa Indonesia version.