10,000 MW

  • 14th May 2009 WIB
10,000 MW
BANTEN, 14/5 - PLTU 10,000 MW. PLTU Labuan Banten Unit 1 with 300 MW capacity, Thursday (14/5), continues to operate after the First Firing process or the first ignition of the plant machine on Tuesday (12/5) at 17.45 WIB. First Firing is implemented faster than the schedule should be on July 11, 2009, while Synchronization will be implemented on 12 upcoming June and Commercial Operation Date (COD) can be done on July – August 2009 or faster one month from the contract on September 2009. ANTARA/Agus/ama/09