ELECTRICITY TOLL CONSTRUCTION SUMATRA
A number of workers feed the cable when the construction of the transmission of sutet tensioned 275 kilovolt Kiliranjao-Payakumbuh in Nagari Timbulun, Sijunjung, West Sumatra, Friday (25/11). A total of 273 towers or 70 percent of the total 373 has entered the rate of cable withdrawal and targeted ramps at the end of 2016, and further will strengthen the central Sumatra system which is part of Sumatra’s electricity toll development. ANTARA PHOTO/Iggoy el Fitra/kye/16