DEVELOPMENT PROGRESS TOLL PALINDRA

  • 4th August 2017 GMT+7
DEVELOPMENT PROGRESS TOLL PALINDRA
Toll road construction of Sumatra ruas Palembang-Indralaya (Palindra) Hot I in the Forestry District, Ogan Ilir (OI), South Sumatra, Friday (4/8). The construction progress of Palembang-Indralaya toll roads is as far as 22.5 km it has reached 59.40 percent while the land exemption progress is 97.68 percent. ANTARA PHOTO/Nova Wahyudi/foc/17.

The caption is automatically translated by application. Click here for the Bahasa Indonesia version.