ELECTRICITY BARRIER 35 THOUSAND MW
A number of PLN officers perform maintenance in Gardu Induk (GI) PLN Tanjung Karang, Mataram, NTB, Monday (25/9). The implementation of the 35 thousand Megawatt electrical projects in the NTB region experiencing obstacles such as rejection of one of the cottage messages that do not want their land to be lined by the transmission line of High Voltage Air Line (SUTT) 70 kilovolt Section Taliwang-Alas as well as forest land problems with the Permit of the Forest Area (IPPKH) rising, but can not be built because there is a claim of ownership by citizens on the SUTT 150 kilovolt Labuhan Empang-Dompu line. ANTARA PHOTO/Ahmad Subaidi/17